Imagine two homes have both sold off the plan and the builder’s next claim is due in a week. The buyer contracts are in the project folder and the cost forecast still shows a margin. The lender’s drawdown has moved seven days because an inspection was delayed. The builder is still expecting payment under the contract. How much cash must the joint venture have ready on the day that bill falls due?
On pages 118 and 119 of Accidental Millionaire, Jason John Byron describes a student who arranged a funded joint venture and presold two proposed homes. The book records those commitments while the project was underway. It gives no completed settlement or realised return for this account. The figures and payment sequence below are a separate, fictional NSW exercise in the funding work taught in the Think Property Club Deal Maker course.
Give each source of money its own date
The student creates three lines in the cash forecast. The first shows deposits and settlement amounts under the buyer contracts and when the project could lawfully use the money. The NSW Government’s off-the-plan guidance explains that a stakeholder holds deposits and instalments under a covered contract in a trust or controlled money account through the contract period. For this exercise, the deposits stay out of construction cash. Ask the project’s solicitor or conveyancer how the actual contract and jurisdiction apply before putting any purchase money into the forecast.
The second line shows what the lender can release, the evidence needed and the realistic receipt date. The proposed draw already appears on the facility schedule. The broker and lender still have to confirm its conditions and release timing. For one example of lender terms, ANZ’s regulated business finance conditions say it may require a valuation or quantity surveyor’s assessment before a residential construction progress payment. The student uses the project’s actual facility and requests an updated written timing estimate after the inspection delay.
The third line shows cash already available for this job and what must leave the account before the draw. The student checks upcoming holding bills and reserves before counting the usable balance. She asks the builder to confirm the claim and its payment date. The Australian Government budgeting guidance describes using a cash-flow statement to forecast receipts and expenses. She uses daily dates here because both sides of the gap fall in the same month.
Calculate what changes when the receipt moves
In this fictional example, the project has $45,000 available after other reserved bills. The builder has a $120,000 claim due on the fifteenth. The forecast draw for this claim is $95,000. If that draw is available to meet the claim on the fifteenth, the project has $140,000 of funds it can apply on that date. After the bill, it has $20,000 available for the next obligations under these assumptions.
When the draw shifts to the twenty-second, the project has only $45,000 to put towards the $120,000 due on the fifteenth. That leaves a $75,000 temporary funding gap. The contracted sales and the forecast draw amount have stayed the same. Moving one receipt date changed the funds available at the moment the claim falls due. This example assumes no further bill before the twenty-second. A real forecast should include each intervening obligation and refresh the dates.
The partners compare two responses while there is still time. They ask the lender whether it can bring the inspection and release forward. They also check what an additional temporary contribution would require under the joint venture and facility. The lender should confirm how the draw would apply if the claim were paid with other funds first. The partners ask their advisers to review the timing and authorisations before counting on either response.
In the exercise, the earlier inspection cannot be booked. The partners decide to proceed with the next stage once a permitted contribution and the draw treatment are confirmed in writing. That outcome belongs to the teaching exercise. The book’s verified case ends with a funded project and two presales under way.
WHAT WOULD A TPC STUDENT DO?
- Ask the project lawyer when deposits and settlement proceeds could become available to the project.
- Get the claim date, inspection date and expected lender release date in writing before updating the forecast.
- Run the dates forward day by day and find the largest cash shortfall before the next release.
- Agree who can authorise extra funding and ask the lender how it treats a claim paid from other funds.
Photographic-style image generated with AI by Think Property Club. The scene is fictional.
Sources and boundaries
Sources checked 15 November 2026.
- NSW Government - Buying property off the plan — NSW guidance on the custody and timing of deposits and instalments under covered off-the-plan contracts.
- ANZ - Regulated Business Finance Conditions of Use — Example lender terms that may require a valuation or survey before a residential construction progress payment.
- Australian Government - Create a budget — Explains cash flow forecasting as a tool for managing receipts and expenses.
The book records a funded joint venture and two proposed-home presales while the project was underway. The figures, dates, funding terms and exercise outcome are fictional.
The ANZ document illustrates one lender’s terms. Check your actual facility, contract and available cash.
The NSW example is fictional and for property development education. Confirm current project requirements with appropriately qualified advisers.
Learn with Jason & AmyBuild practical small-scale property development skills with experienced mentors.Enquire nowRate this article
Guest rating: select 1 star for poor or 5 stars for great. No account is required.
Leave a comment
Join the discussion. Your email address will not be published.
Frequently asked questions
Can the project use deposits to pay the builder?
In the covered NSW example, deposits are held by the stakeholder during the contract period. Ask your lawyer how the project’s terms and jurisdiction apply.
Which date matters for a draw?
Use the date funds are expected to be applied to the claim, after any inspection and conditions, and check it with the lender.
What if both transactions happen in the same month?
Forecast on the specific days involved. A month-end balance can hide a gap between the claim and the draw.
How big is the gap in the example?
The builder is due $120,000 and the available cash is $45,000 on that day. The gap is $75,000.
What if partners pay the claim before the funds arrive?
Ask the lender and advisers how the draw will be treated and what the facility and joint venture allow before assuming reimbursement.